Eric,
When I said 'what is RLD date' I meant "what is 'RLD' an acronym for". This is not a standard SAP acronym/abbreviation.
You are very quick to say there is no issue with factory calendar. Are you saying that you have examined all calendars that possibly could have an impact on this issue, and have determined that they are EXACTLY the same?
We can evidently ignore for now delivery and transportation scheduling, since you have asserted that 'transit time' (whatever that means) is the same. FYI the scheduling of the duration between "material availability date' and 'delivery date' is typically dependent upon several events and at least two durations; sometimes more.
You did not answer my question about start dates.
You earlier stated that both material masters were the same. Now you are saying that one is MTO and one is not. Can you please elaborate?
Best Regards,
DB49