This could be due to validity of your production version. I think non of your production version in plant 1300 is valid on current date. I have tested the same by changing the validity of production version to current date then I could see all the columns are gray out expect 18.05.16 as this date my PV is valid.
Please cross check the validity of your all production versions in C223 for plant 1300 and extend the validity in future date and then execute the MFS0.